Month: January 2013

Xcel Energy Training Facility Phase II and Phase III.

Phase one was recently completed which included VAV roof top units with hydronic reheats.  This project is a LEED project.  Phase II and Phase III will be new facilities with infrared heating, CO/NO2 exhaust and make up air. Will utilize roof top units for heating and cooling.

CH Robinson

New building is currently under construction and is part of CH Robinson’s existing campus. It will be approximately 81,000 sf.  Mechanical system will be a VAV system with electric heat.